Distributed Generation Interconnection Procedure

​If you are an individual or represent a company interested in interconnecting a distributed generator (DG) of 15 MW or less to the utility grid, please follow these steps:

1. Review PSC Chapter 119 of the Wisconsin Administrative Code (see link below) and the DG Interconnection Guidelines.

2. Contact the electric utility or cooperative association (electric provider) serving your DG site to obtain the proper application and agreement forms.  The "DG Points of Contact" document below contains the necessary information for each electric provider in Wisconsin.

3. The application and interconnection agreement forms are for information only.  Please contact your electric provider to obtain the appropriate application and interconnection agreement forms.

4. Mail forms directly to the utility.

Distributed Generation Points of Contact

Wisconsin Administrative Code: PSC Chapter 119

Distributed Generation Forms

PSC Contacts:

Jim Lepinski, Chief Engineer
(608) 266-0478
jim.lepinski@wisconsin.gov