Racine County Western Feed Project

​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​< Highlighted Cases
Image of Wisconsin map and highlighted county

Counties of Buffalo and Trempealeau​, Wisconsin

Docket ID: 137-CE-209

Application of American Transmission Company LLC, as an Electric Public Utility, for a Certificate of Public Convenience and Necessity to Construct and Operate the Western Feed Transmission Line Project, Consisting of Two Sets of Double-Circuit 345 kV Transmission Lines, One Set of Double-Circuit 138/345 kV, and One Single-Circuit 345 kV to Interconnect the N​ew Jupiter and Cosmos Distribution Substations Located Primarily in the Villages of Yorkville and Mount Pleasant, Racine County.​​

View and Downl​​oad Proj​ect Map​​

Jump to Section:


Interactive Map

Use the interactive map to explore the​​ project.

Tips for using the map

  • Click the tiles in the upper left hand corner to Zoom i​n, Zoom out, return to the Default map view, or use the Find my location function.​
  • Click the tiles in the upper right hand corner to Search and Find address or place, toggle on/off Layers, choose a different Basemap, or Measure distance and area.​
​​ ​​
​​
​​​View Map i​n New Window

Application Summary

Overview

American Transmission Company (ATC or applicant) is seeking approval to construct two new substations, named the Jupiter and Cosmos substations, and multiple new transmission lines to interconnect the new substations to existing facilities. Each substation would have a 33.5-acre site. Two new double-circuit 345 kilovolt (kV) transmission lines would connect ATC’s existing Paris-Arcadian 345 kV line (W-30) and Pleasant Prairie-Arcadian 345 kV line (PLPL81) to the new Jupiter and Cosmos substations. New 138/345 kV double-circuit transmission lines would interconnect the new Cosmos substation to ATC’s existing Mount Pleasant substation. The project would also require a new 345 kV single-circuit transmission line, which would be designed for an ultimate double-circuit configuration, to interconnect the new Jupiter substation to ATC’s existing Mount Pleasant substation. The Proposed Route would be 3.6 miles in length including a total Right-of-Way (ROW) of approximately 152 acres. The Alternative Route would be 3.7 miles in length including a total of 159 acres of ROW. The Common Route would be 6.0 miles in length including a total of 171 acres of ROW. The routes are occurring almost entirely within new ROW, ranging between 0 percent shared and 3 percent shared with existing ROW depending on the route.

Applicant stated need

The project is needed to support multiple large new load additions within the Electronics and Information Technology Manufacturing Zone (EITMZ) requested by We Energies in southeastern Wisconsin.​

Estimated cost

The applicant stated that the estimated project cost would be approximately $593.8 million if the proposed route is selected and approximately $621.9 million if the alternative route is selected.

Project location

The project would be located in the Villages of Yorkville, Mount Pleasant, and Sturtevant in Racine County, Wisconsin.

Proposed schedule

  • The applicant submitted the application to the Commission in July 2024.
  • ​If approved, the applicant anticipates construction for this project to begin in November of 2025 and be completed by December of 2026 for the transmission lines, and by June of 2028 for the new substations.​
Statutory Review​​​

The Project is categorized as a Type II action under Wis. Admin. Code § PSC 4.10(2). The Commission will prepare an EA for this project that will evaluate the location of the project and its potential environmental, community, and private property impacts. There will be a preliminary determination when the Environmental Assessment (EA) is complete that will determine whether the preparation of an Environmental Impact Statement (EIS) is necessary.


Key Application Documents


Case Contacts and Additional Information

Access Docket 137-CE-209​ in the PSC Case Management System to view​ additional information.

Utilize the Staff Involved tab for contact details for PSC staff assigned to the docket, including the case coordinator and the environmental review coordinator.

Click the Documents tab for a complete list of docket documents categorized by document type.​

Access Doc​​ket 137-CE-209​​​​​​​​

Opportunities for Public Participation

The Commission offers several opportunities for public participation in its proceedings. Click the links below to stay updated on these opportunities, which may include providing input regarding the scope of environmental impact documents, attending public hearings, offering comments, or signing up for email notifications related to a particular case.​

​ ​​

< Highlighted Cases
​​