Portage Solar Project

​​​​​​​​​​​ < Highlighted Cases

Final Decision Issued

On April 10, 2023, the Commission issued a final decision for this project. At the time of final decision, the anticipated start date of construction was Summer of 2023 with completion by Summer of 2024​.

Quarterly construction updates and post decision correspondence between the Commission and the Applicant can be found in the corresponding docket reports.

Docket Reports: 9810​​-CE-100

Towns of Grant and Plover in Portage County

Docket ID: 9810-CE-100

Application for a Certificate of Public Convenience and Necessity of Portage Solar, LLC to Construct a Solar Electric Generation Facility in the Towns of Grant and Plover, Portage County, Wisconsin​.

View and Download Project Map

Jump to Section:


Interactive Map

Use the interactive map to explore the project.

Tips for using the map

  • Enter a location or address in Find address or place to zoom into specific location.
  • Click the information button () under the search bar to view additional guidance and tips for using this mapping application.
​​ ​
View Map in New Window

Application Summary

Portage Solar is seeking approval to construct, install, operate, and maintain the Portage Solar Project, a 250-MW photovoltaic (PV) solar energy generating facility in the Town of Grant and Plover, Portage County, Wisconsin (“Project”). The Project, which is anticipated to be placed in service as early as November 2024, would be constructed on 2,167 acres of primarily agricultural land. In addition to the solar panel arrays, several new structures would be required for the project including a new on-site substation, an Operations and Maintenance building (O&M), and a Battery Energy Storage System (BESS). Additional components including power conversion units, inverters, underground collector circuits would be constructed adjacent to the solar panel arrays. The project would require the construction of a new 500 foot, 115kV gen-tie line (a new electric line to transmit energy generated by the facility to the existing electric transmission grid).

Applicant stated need: This project is proposed by an independent power producer Portage Solar, LLC, a wholly owned subsidiary of National Grid Renewables. As such, the need for the project is not reviewed by the Commission.

Estimated cost: This project is proposed by an independent power producer, and the Commission does not review the project cost or need. The cost to Wisconsin Utilities, and ratepayers, would be reviewed if the facility is proposed to be purchased by a Wisconsin Utility, or Utilities.

Project Location: The proposed project is located in the Towns of Grant and Plover in Portage County, Wisconsin (see maps below).

Proposed schedule:

  • The application was submitted to the Commission in March of 2022.
  • If approved, the proposed construction schedule for this project would begin in August of 2023. The project is proposed to be completed and in service by November of 2024.
Statutory Review

This is a Type II action under Wis. Admin. Code § PSC 4.10 (2). The EA will be prepared to determine if an environmental impact statement is necessary under Wis. Stats. § 1.11.


Key Application Documents


Case Contacts and Additional Information

Access Docket​ 9810-CE-100 in the PSC Case Management System to view additional information.

Utilize the Staff Involved tab for contact details for PSC staff assigned to the docket, including the case coordinator and the environmental review coordinator.

Click the Documents tab for a complete list of docket documents categorized by document type.

Access ​Docket 9810-CE-100