Akron Solar Project

​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​< Highlighted Cases
Image of Wisconsin map and highlighted county

​Town of Rome, Adams County, and Town of Saratoga, Wood County, Wisconsin

Docket ID: 9832-CE-100

Application of Akron Solar, LLC for a Certificate of Public Convenience and Necessity to Construct a Solar Electric Generation Facility Capable of Generating Up to 200 MW, a Collector Substation, a Generation Tie Line, and a Battery Energy Storage System in the Town of Rome in Adams County and the Town of Saratoga in Wood County, Wisconsin​.

View and Download Proj​ect Map​​

Jump to Section:


Interactive Map

Use the interactive map to explore the​​ project.

Tips for using the map

  • Click the tiles in the upper left hand corner to Zoom in, Zoom out, return to the Default map view, or use the Find my location function.
  • Click the tiles in the upper right hand corner to Search and Find address or place, toggle on/off Layers, choose a different Basemap, or Measure distance and area.​​

​ ​​
​​

​​​View Map i​n Ne​w Window

Application Summary

Over​view

Akron Solar, LLC, a wholly owned subsidiary of NextEra Energy Resources​, is seeking approval to construct a solar energy generating facility with a generating capacity of 200 MWAC (megawatt alternating current) in the Town of Rome in Adams County and the Town of Saratoga in Wood County, Wisconsin. The project study area that was evaluated is approximately 2,409 acres, of which, the proposed project arrays make up 1,347 acres, and the alternative project arrays make up 344 acres. The major components of the proposed project include solar photovoltaic (PV) panels, inverters, approximately 23 miles of underground 34.5 kilovolt (kV) collector circuits, a 200 MWAC battery energy storage system (BESS), a 138kV project substation, an approximately 1.8-mile 138 kV gen-tie transmission line to connect the project substation to the existing distribution grid, access roads, and an operation and maintenance building. The proposed project includes four proposed array areas and one alternative array area. Array areas can be seen in the attached map.​

Applicant Stated Need

This project is proposed by an independent power producer. Therefore, the need for the project is not reviewed by the Commission.

Estimated Cost

This project is proposed by an independent power producer. Therefore, the Commission does not review the project cost. The cost to Wisconsin utilities, and ratepayers, would be reviewed if the facility or power from the facility is purchased by Wisconsin utilities.​

Project Location

The applicant proposes to construct this project in the Town of Rome in Adams County and the Town of Saratoga in Wood County, Wisconsin.

Proposed Schedule

  • The applicant submitted the application to the Commission in April 2024. 
  • If approved, the applicant anticipates construction for this project to begin in Q4 2027 with an estimated completion date of Q3 2029.
Statutory Review​

This project​ is categorized as a Type II action under Wis. Admin. Code § PSC 4.10(2). The Commission will prepare an EA for this project that will evaluate the location of the project and its potential environmental, community, and private property impacts. There will be a preliminary determination when the Environmental Assessment (EA) is complete that will determine whether the preparation of an Environmental Impact Statement (EIS) is necessary.


Key Application Documents


Case Contacts and Additional Information

Access Docket 9832​-CE-100 in the PSC Case Management System to view​ additional information.

Utilize the Staff Involved tab for contact details fo​r PSC staff assigned to the docket, including the case coordinator and the environmental review coordinator.

Click the Documents tab for a complete list of docket documents categorized by document type.​

Access Doc​ket 9832​​-CE-​​100​​​​​​​​

Opportunities​ for Public Participation

The Commission offers several opportunities for public participation in its proceedings. Click the links below to stay updated on these opportunities, which may include providing input regarding the scope of environmental impact documents, attending public hearings, offering comments, or signing up for email notifications related to a particular case.​


​​​​​
< Highlighted Cases