Distributed Generation Interconnection Procedure
If you are an individual or represent a company interested in interconnecting
a distributed generator (DG) of 15 MW or less to the utility grid,
please follow these steps:
1) Review chapter PSC 119 of the Wisconsin Administrative Code
(below) and the DG Interconnection Guidelines (see widrc.org).
2) Contact the electric utility or cooperative association (electric
provider) serving your DG site to obtain the proper application
and agreement forms. The "DG Points of Contact" contains
the necessary contact information for each electric provider in
Wisconsin.
3) The application and agreement forms below are for information
only. Please contact your electric provider to obtain the appropriate
application and agreement forms.
|